
|
|
History and Statistics of The Severn BridgeOriginal Construction Details The Severn Bridge was opened by the Queen on the 8th September 1966 to replace the ferry service crossing from Aust Cliff to Beachley Peninsula, 8 miles upstream from Avonmouth. At this point the River Severn is almost exactly 1 mile wide at high water and the bridge creates a direct link for the M4 motorway into Wales. The Severn Bridge is in fact two bridges. The main section spans the Severn Estuary, whilst the second smaller section spans the River Wye. The Severn Bridge Bridge General Dimensions
Design Loading Two 24 ft wide carriageways, one 12 ft wide footway and on 12 ft wide cycle track.
Aust Pier A concrete monolith, 132 ft long, 40 ft thick and 63 ft high from its founding level of 18 ft O.D. oblong in shape with pointed cut-water ends. Founded on a limestone outcrop in the river bed known as Great Ulverstone. Construction was by means of precast blocks placed to form the outer skin and then "hearted" with in-situ concrete. Work was tidal during earlier stages. The pier is stressed down to the rock by 58 1 1/4 inch MacAlloy bars round its periphery, grouted 12 ft into the rock and stressed to a force of 45 tons each. Beachley Pier A concrete monolith similar to that of Aust Pier but resting on two 60 ft diameter concrete cylinders extending approximately 33 ft downwards from the river bed to a founding level at -50 ft O.D. Founded on hard mudstone of the Keuper Marl series. Anchorage Of the gravity type, these appear externally as roughly rectangular blocks of concrete, 155 ft long by 110 ft wide and extending up to a level of 132 ft O.D. The Aust anchorage is at a level of -8 ft O.D. 550 ft offshore of Aust Cliff. A three span viaduct carries the roadway between the Anchorage and the cliff. The Beachley anchorage is found on limestone approximately -20 ft O.D. Towers The towers are constructed of high tensile steel with a yield stress of 22 1/2 tons per square inch. The thickness of the steel in the legs varies from 1 inch to 9/16th of an inch. Each leg is a single hollow box, 17 ft by 12 ft at the base, tapering to 17 ft by 9 ft 6 in at the top. The sides of the box are bolted together at the corners on inwardly turned seams so that no bolt or nut is exposed on the outer side. The bolts are mostly 7/8 of an inch in diameter. The transverse portal members are also hollow box sections. The towers were erected in sections of 55 ft 6 inches long by climbing cranes. The bottom of the legs are held down to piers by 1 1/8 inch diameter pr-stressed strands, penetrating 50 ft into the concrete and post tensioned. The legs are capped by saddles which carry the main cables. The saddles are 443 feet above mean water level. Each tower carries a vertical dead load of 13,200 tons and each weighs 1,300 tons. Approximate Material Quantities
Contractors and Cost
|
||||||||||||||||||||||||||||||||||||
| Current Bridge Status | ||
|---|---|---|
|
M48 Severn Bridge:
|
||
|
M4 Second Severn Crossing:
|
||
| Recent News Update |
|---|