Severn Bridge and Wye Bridge Strengthening Work 1985-1991

Development in Road Transport in the 1960's and 70's

There were some remarkable changes in the freight transport pattern soon after the Severn and Wye Bridges were designed. Between 1962 and 1977

  • the amount of goods moved by road measured in tonne km virtually doubled
  • the number of goods vehicles with a gross weight of 28t rose from an insignificant amount to 90,000
  • those under I It gross weight fell substantially in number

Investigation into Bridge Structure in the 1970's and 80's

The Department of Transport commissioned independent consultants Flint & Neill to carry out an appraisal of the Bridge structures in the light of changes to traffic loading pattern. There were also changes to bridge design criteria to he addressed as a result of the findings of the Merrison Committee. The final report of the Consultants indicated that in order to maintain the required margin of safety under the worst possible loading conditions various parts of the Bridges would require strengthening or improvement. This involved the following changes to the various structures in the crossing.

(a) Installing a tubular column approximately 120 meters in height at each corner of the four Towers so that some 25% of the loading initially in the tower shell was transferred to the foundation via the tubular columns.

(b) The inclined hangers which transfer the load in the roadway deck boxes to the two main suspension cables were replaced with larger ones with improved designed sockets at either end.

(c) A particular welded joint detail in the roadway deck boxes immediately below the wheel tracks had been found to he susceptible to fatigue damage. These welds were removed and replaced with an improved designed welded joint.

(d) The ends of the roadway deck boxes at the Towers are supported and connected to the Towers via the lower horizontal portal between the Towers The connection is made via a vertical beam, one end that is attached to the end deck box and the other to the portal. The bearings at each end of the beams were replaced with modified bearings to allow for rotation about the longitudinal and transverse axis as a result of the movement of the roadway deck

(e) The original single cable stay system on the Wye Bridge was replaced with a harp‑ like arrangement, which involved increasing the height of the Towers and the constructing a further four cable anchorage's to make up a total of eight.

(f) The complete crossing was re-surfaced using a mastic asphalt specification above a waterproof membrane bonded to the steel deck plate. This arrangement is designed to act in composite action with the steel deck plate to distribute vehicle wheel generated stress in the deck plate structure.

Reference 1 Inquiry into the basis of design and method of erection of steel box girder bridges HMSO 1971 Interim Report.

 
     
Current Bridge Status

M48 Severn Bridge:

The bridge is open to all traffic, which is believed to be flowing freely

M4 Second Severn Crossing:

The bridge is open to all traffic, which is believed to be flowing freely
 
Recent News Update
 
Maintenance and Closures
There are currently 3 advisory notices for lane closures on the M48 Severn Bridge, with 1 serious warning of complete carriageway closure.

There are currently 0 advisory notices for lane closures on the M4 Second Severn Crossing.